DLA CONSOLIDATED WAREHOUSE AT

PORTSMOUTH NAVAL SHIPYARD

Kittery, Maine

Project Summary:  

This project is a 29,200 SF addition to the existing warehouse Building 170. The project consists of constructing a one-story, high-bay steel framed storage warehouse addition with an insulated pitched metal standing seam roof set on a reinforced concrete floor slab and foundation to match the existing warehouse. 

The project completes the consolidation and modernization of a submarine component processing facility that will enhance the joint ability of the DLA and Navy to receive, inspect, and distribute submarine components for worldwide fleet support.

The project was designed by Naval Facilities Engineering Command Mid-Atlantic and was awarded to Cianbro Construction of Pittsfield.  Building Performance Advisors is part of the engineering team providing Building Envelope Commissioning and testing services.

Project Budget:  $17.3 million

Project Team:

Owners:  AVFAC Mid-Atlantic Naval Facilities Engineering Command

General Contractor:  Cianbro

Engineer:  Naval Facilities Engineering Command Mid-Atlantic

Commissioning Agent:  Building Performance Advisors